MGT 311 Saudi Electronic University Network Diagram Report
Description
Assignment Question(s): (Marks 5)
A public accounting firm requires the following activities for an audit:
Activity |
Immediate Predecessor |
Activity time |
A |
– |
3 |
B |
A |
2 |
C |
– |
5 |
D |
B, C |
2 |
E |
A |
4 |
F |
B, C |
6 |
G |
E, D |
5 |
- Draw a network for this project? (Marks 2.0)
- Make a forward pass and a backward pass to determine ES, LS, EF, and LF? (Marks 2.0)
- What are the critical path? (Marks 1.0)